In the early 19th century, the
barn was a symbol of permanence and prosperity. English threshing barns such
as this one, were once common on farmsteads in Upstate New York. These barns
had three bays with large swing doors opening onto the center bay. Grain was
processed, or threshed in the center bay and stored in the mows and lofts.
According to old maps, the Bements built their threshing barn across the
road from the house. It was destroyed by fire many years ago. The barn we
have now, was built in the early 1800’s by the Herrick family of Candor, New
York. It was dissembled and reconstructed on the farmstead property in the
late 1990’s. The frame was re-erected at a traditional barn-raising during
the 1999 Spring Festival. Members of our Blacksmith’s Guild reproduced
hardware for the structure.
After years of being hidden within the walls of a working dairy barn, the
Herrick threshing barn can be seen once again, as disassembly and relocation
takes place.
The main barn (30 X 70) as seen from the north side. The original
threshing barn (30 X 40) faces north with the addition (30 X 30) facing
south. The clapboard siding was probably added in the 1920's. The horse
barn (originally a blacksmith shop, but now a garage) runs off to the
east. Although not visible the horse barn has a lean-to addition on the
opposite side. This picture was taken in November 1995. Disassembly
began on August 1, 1996.
Most of the clapboards have been removed along with most of the
siding on the 30' addition. The two sections of the main barn are now
more readily visible.
This shows the frame of the 30' addition. It was recycled from
another barn, perhaps around the turn of the century. These rafters are
poles that were flattened on one side rather than being sawn timbers.
This is the part where the dairy herd was placed. Recycling of timber
frames was quite common.
Frame of the addition taken from the south.
With the frame of the addition removed, the framing of the original
threshing barn is now clearly visible. In the center is the threshing
bay, where the grain was processed; the right bay was for storage of
straw or hay; the left bay (the narrower one) would contain the granary
and stable area.
Another shot of the frame taken from the south. The tie beam facing
us was cut to accommodate the hay track.
The rafters have been removed and the frame is now ready for final
disassembly. Randy Nash, our contractor, can be seen in the foreground.
Final disassembly was done with a crane. Care must be taken to
remove enough braces to speed the process without making the frame
unsafe to walk upon.
Another view of the crane at work. The date was August 14, 1996.
View of the horse barn with west side completely exposed. Lean-to
addition is now clearly visible.
Horse barn has been enclosed using clapboard siding that was saved
from the main barn. The foundation of the main barn has been buried,
leveled and reseeded. This picture was taken in late October, 1996.
A wall of fieldstone is carefully laid up, forming the new foundation for
the Herrick Barn.
A trench between 30" and 40" deep and measuring 32' X
42' was dug in August 1998. It was filled with #2 stone and lined with
geocloth. The geocloth keeps dirt from filtering into the trench over a
given period of time. The trench is two feet wider than the barn
foundation (30' X 40') because having #2 stone about a foot or so around
the perimeter of the barn will help with drainage. If the "old-timers"
had backhoes and gravel they would have done something similar. None of
this "modern" foundation work will be seen by the public.
Kevin Reilly of Newfield, NY, received the bid for the stone wall.
He started work during the Society's Apple Festival in October.
Kevin has completed the northwest corner. This first
corner is important because it establishes the height and orientation of
the entire foundation. The minimum height to help preserve sill timbers
should be 8" to 10" above grade. There is a 20" difference in grade on
the site, making the west wall that much higher than the east wall.
During the Festival, William Bement, master of the
Farmstead, came to inspect the work. The foundation for the Herrick Barn
is essentially a double wall with a dead air space in between filled
with #2 stone. Larger field stones are used for the base which is
approximately 6" to 8" below the surface. The stones taper inwards to
help with stability and drainage and the wall narrows as it reaches the
correct height.
Kevin also ran a stone wall workshop the following
weekend. His assistant was Michael Williams. The workshop had nine
participants.
The wall was essentially finished on October 25 during
the Society's Haunted Barn activities. The stone came from four
different sites. Much of the east wall is from the Herrick Barn's
original site. The rest of the stone came from three different Newark
Valley families: Bob and Paula Lawrence, Bob and Kathy Card and the Snapp family. This amount of stone would be valued at $2,000.
The wall was covered with construction cloth and winter wheat was
planted around the foundation grading. Back in pioneer days this was
probably ground that was planted for wheat as well.
From the beginning of the project it was the wish of the Society to have a
traditional barn raising. This is certainly in keeping with the philosophy
of a living history site and with the concern we had developed for
historical authenticity and accuracy.
Dick Warner, an experienced timber framer and one of the organizers of our
Woodwright Guild, was willing to lead the raising. He had led a crew of
inexperienced people assemble one of his own frames, but had never done a
completely traditional raising.
We decided to do the raising as part of the Society's Spring Festival on
June 12-13, 1999. This actually coincides with a traditional time for
raisings that often occurred between planting and the start of hay
gathering.
The frame is not exceptionally large (30' X 40') and the timbers themselves
are of moderate dimensions. Since pine is fairly light in comparison to
hardwoods, Dick did not feel that use of a gin pole would be necessary.
The work crew numbered 30. Six were experienced timber framers and seven
were from our woodwright guild. The ages ranged from 17 to 67 and included
two members of the Herrick family. Our 17 year old was John Tomazin. He has
been one of our most active Youth Interpreters, a program developed by the
Society for young people to learn traditional crafts and help interpret the
Farmstead for the general public.
The frame would be erected in much the same fashion as it had been done 175
years before. There were these exceptions: the crew would wear hardhats,
there was a woman on the crew, and there was no barrel of hard cider sitting
under a tree.
We encouraged everyone to meet the Saturday before the raising, especially
those who lacked experience. The first job was to draw the sills true and
then bring the floor joists into place. This was the type of job that works
well with extra bodies and it gave the participants a chance to work with
one another. A temporary floor was then put into place and the first bent
assembled. We practiced a lift. We picked it up, raised it over our heads
and brought it back down. It helped give us confidence for the real thing.
Floor joist placement done on June 5. The two principal joists
could be reused, but five others were taken from trees in the Farmstead
woods and hand hewn on one side. Half of the sill material was replaced
or recreated as well.
The plan for the weekend was to have the bents and plates up on Saturday
and the queen posts, purlins and rafters in place on Sunday. We wanted the
public to see the process from the very beginning and had advertised that
the first bent would go up at 10:30.
The Raising - Bent #1 (June 12th)
The weather was ideal for our Spring Festival weekend. It was warm, but not
excessively hot and more important, there was no rain in the forecast.
We took our positions on the temporary floor. Earlier the crew had raised
the bent on a pair of saw horses. This was a big help because there is a
point where your hands need to move from lifting the bent to pushing the
bent. The saw horses do not eliminate this, but it makes this transition
much smoother.
One member of our crew, Tom Bartenstein, has quite a flair for history, and
came dressed in the garb of the early 1800's. He cut quite a figure with
knickers, buckle shoes and period shirt topped off with a florescent yellow
hard hat. He was dressed as Theodorus, of course. It was only fitting that
the man who built the barn should be present at the raising.
First bent has been assembled, raised on saw horses and is ready for
lifting at 10:25 A.M.
At 10:45 the call went out to begin the lift. A raising is a very
interesting illustration of team work. Although we had a good mix of
experienced people, it was important to have the raising process
orchestrated by the leader. This would help decrease the chances of
accidents or mistakes. The first part of the process a group of individuals
hand lift the bent. The weight of the bent determines the number of people
necessary for the lift. Once the bent is over the heads of the hand lifters,
the pike poles need to be utilized. These are people who stand behind the
hand lifters and make the first contact to bring the bent into a 45 degree
angle. Their poles are short ones.
The hand lifters need to drop back, grab one of the longer pike poles and
continue the process until the bent is nearly vertical. As a safety measure,
two people have ropes attached to end posts to help keep the bent from going
completely over. At the same time, other individuals need to be positioned
where the post tenons will drop into the sills. Often brackets are nailed to
help the process, especially for short studs. Once the bent is vertical, a
temporary brace is nailed at a 45 degree angle to the sill to stabilize the
bent. This is one of the most precarious times in a raising. Until the
second bent is in place with girts attached to the first bent, there isn't
much keeping the first bent stable.
Once the bent is being raised it is important to maintain momentum. It
becomes very dangerous to slow down. It also highlights the need to check
everything a dozen times. You don't want to have the bent in place and
suddenly realize that something is amiss. A time consuming repair or
adjustment at this point loses valuable time and can be very hazardous.
Proper handling of a handling the pike pole is critical. To maintain
adequate control, keep the hands spread apart and keep them stationary.
Going hand over hand can cause the pike pole to slip and subsequently drop.
This not only causes a loss of pressure on the bent, but could also drop on
a member of the crew.
Raising of bent #1 10:45 A.M.
Everything went smoothly. Within a few minutes the bent was vertical, the
post tenons had dropped into the sills pockets and a temporary brace had
been nailed. There was some problem with a center post, however. This is
where the use of a commander or beetle is utilized. It is a large mallet
with a huge wooden head designed for those parts of the frame that aren't
cooperating quite the way that they should. It certainly gets the job done.
Girts are nailed in place temporarily until they can be connected to
bent #2.
Bent #2
Next came the assembly of bent #2. While part of the crew was involved
with bringing over pieces of the frame, others were moving floor boards and
several others were getting the girts in place that would stabilize the
first two bents. This bent had more studs that helped enclose both the
granary and stable area. Once again the bent was lifted on saw horses. Crew
members on either side would help align girts for placement into the posts.
Bent #2 rose the same way as bent #1. Within a few minutes the girts were in
place and wooden pegs had been driven into their respective holes. With two
bents stabilized, the frame was off to a good start. The time was 11:40 and
it was time for lunch.
Raising of Bbent #2 as seen from the south side of the barn. Note the
studs for the stable and granary wall.
Bents #3 & #4
By early afternoon we were ready for bent #3. The pattern for having the
bents move into position followed a standard formula: a temporary floor was
moved into place, the bent was assembled and placed on saw horses. Each one
did have special characteristics, however, that made them unique in some
way. Bent #3 had the built-in ladder for climbing into the mow bay. There
was also a series of studs for the breast wall on either side. This bent was
attached to bent #2 with a single 14' girt that straddled the threshing
floor.
Bent #3 in position 2:00 P.M. Note the ladder and short breast wall.
The first three bents were raised with the crew facing south. This would
not be feasible for bent #4 because of the proximity of the Norway spruce.
Fortunately there was just enough room in the mow bay to accommodate the
bent, but it did make it a bit difficult to grab pike poles once the raising
began. One pike pole became lodged between the tie beam and the breast wall
girt. If the angle had been too great it might have broken the pole, but
very soon it was worked free.
Bent #4 in position, and girts connected.
Attaching the girts for these two bents was a bit more problematic. The
bent needed to be pushed back from the vertical to accommodate the
appropriate tenon. This required some pike polers to go to the opposite
side. It also kept the people holding the ropes on their toes. Wooden pegs
helped secure the structure. It was 3:00 PM and all the bents were in place.
So far so good.
Photos of a bent #3 being raised at Ray Stannard's farm,
Newark Valley, taken in the early 1920's. Although they had a larger
crew, the raising process was essentially identical.
The Plates
We were on schedule for the plates and this is where a raising becomes even
more interesting. The bents can be erected from the ground with a few people
working from ladders or step ladders. For the rest of the structure, a
number of people need to work 13' or more off the ground. Not everyone feels
comfortable working from a scaffold. The people that are experienced and
feel at ease with this task automatically climb up the frame, but for more
than one person it took some time to get their "sea legs".
Photo of a plate being raised at Ray Stannard's
farm, Newark Valley, taken in the early 1920's.
Plates can be brought up in one of two ways: pull the framing piece straight
up to the top or pull up one side, tie it off and then pull up the other
side. We had eight crew members, two at each post, who pulled the plate in
one motion. The plate that went to the east side had been damaged by water
seepage in the section over the threshing floor. During frame repairs, the
deteriorated wood had been gouged out, and a large piece of white oak
dropped inside of it for reinforcement. Carriage bolts helped secure it and
would be the only visible sign to the public that a repair had been made. As
a safety precaution, two boards were clamped over this area during the lift.
Once everything was in place, ropes were fastened in four places and the
plate was lifted onto a pair of saw horses. When the word went out to lift,
the ropes went taunt and people from below helped with hand lifting and soon
after grabbed a pike pole.
It was important not to stop until the plate could be positioned on top of
the posts. The plate was tied so that the mortises of the plate would fit
over the tenons of the posts once the plate was lifted high enough. If this
doesn't happen, the plate needs to be turned in midair into the appropriate
position. Besides getting the plate over the post tenons, there are four
braces that need to be placed as well. The general procedure is to start on
one side with one person guiding the plate into the post and his partner
making sure that the brace falls into the right slot. When this is done the
procedure follows its way down the plate until the opposite end is secure.
Nobody wants to work longer than necessary, but no one wants to make a
mistake either. The plate dropped into place with gravity doing most of the
work.
Raising of the east plate 3:55 P.M. Eight crew members lift from above while
others are hand lifting and using pike poles from down below.
Next came the west plate. This plate had a 6' section that had been cut out
when the threshing barn had been joined to another barn (see Timber Frame
Barn Disassembly). It could be brought to the top in three pieces. Before
this was done, however, scaffolding needed to be brought to the opposite
side. When barn raisings were common place, there are frequent references to
individuals that displayed various degrees of acrobatic skill from the
frame. This was all part of the show and one of the features that would help
draw a crowd for the event. Perhaps it was a chance for people who had
always wanted to be part of the circus to fulfill some latent desires.
Bringing up the west plate was a piece of cake, comparatively speaking. The
three pieces could be brought up separately and pegged together once they
were dropped into place. It was 4:35 and time to take a well deserved rest
from a very successful day.
Raising of west plate. Scarf joints connected the new replacement section to
the two original pieces.
We took a shot of the barn raising crew because some of the people would not
be able to participate the next day. Our crew shots were taken from the
southwest corner. This was about the best place to get everyone into the
picture. The traditional shots of barn raising crews have people draped all
over the frame from rafters to floor.
Barn raising crew Saturday, June 12.
Queen Post Assemblies (June 13th)
Sunday would turn out to be as nice a day as the one before. The morning
would be involved with queen post assemblies, which consist of two queen
posts, a girt and two braces. The pieces were lifted, posts and girt
assembled and each one raised into place. These might be described as
mini-bents and each involved a separate raising. One crucial difference was
that the crew was 13' off the ground. Four people were needed to raise each
assembly with two others to make sure braces were in place.
Sunday, June 13, the first queen post assembly is in place. It consists of two
posts, a girt and four braces.
The queen post assemblies went up without mishap or any real excitement.
That was the way we wanted it. The only variation was assembly #3 that had a
ladder going up to the girt. This had been in the original threshing barn,
but it along with the girt had been removed for installation of a hay track,
probably some time in the early 1900s. By 12:40 three of the assemblies were
in place and lunch was served.
Raising of queen post assembly #3 with restored ladder and girt.
Purlins
The last major task was the placement of the 40' purlins. This is a major
piece of the frame that rests on the queen posts. Although of smaller
dimensions than the plates (7" X 8" rather than 7" X 11"), the purlins
needed to picked up six feet to the top of the queen posts in an area that
was a bit tight for working. First the eastside purlin was pulled up along
the side wall just as the plate had been done. After moving the scaffolding
the purlin was placed on saw horses. When everyone was ready, the purlin was
set atop the posts and certain people needed to sure that braces were in
place. Working from one end to the other, this part of the frame was now
secure. Placement of the west side purlin was a repeat performance of the
eastside.
Raising of the east purlin 2:45 PM Although of smaller dimensions
than the plate, the work area was more awkward and the piece had to be
lifted 6' high.
Rafters
After the purlins had been secured, placement of the rafters seemed
anti-climatic. Once scaffolding was placed along the queen post girts, the
rafters dropped in place over the plate and purlin. A half lap joint kept
them secure at the top.
Frame with west purlin in position 3:30 PM. Rafters prepared for assembly.
It was about this time that William Bement a.k.a. Ed Nizalowski, the master
of the Farmstead, made an appearance out the back door. He chided the crew
for not having a barn built soon enough for the crops that were ripening in
his fields. The rest of the time was spent glad handing quests. Since
Theodorus had been there on Saturday, William needed to come back to life at
least one day himself.
When the final rafter was in place, it was time for the tradition of the
green bough. Tom Dinmore had the honor of nailing a branch from the Norway
spruce to the final rafter.
Tom Dinmore of Tioga Center, NY, nails the
green bough to the finished frame.
This is a very old tradition dating back to at least the middle ages and is
taken from Germanic and Scandanavian culture. It signifies honor and respect
to the forest from which the frame has been fashioned. It may also be a way
of bringing vitality and life to the new frame. It's meaning and symbolism
spring from the same culture that brought us the Christmas tree. After this
the crew gathered for another photo.
Rafters in position; frame complete! 4:30 P.M.
Barn raising crew Sunday, June 13.
Meaning of the Frame
The raising of the frame is the climax of barn construction. It's the
component where the greatest number of factors need to be coordinated and
must function as a unit: a crew must be assembled, they must be fed, the
weather must cooperate, the frame must be ready, the people in charge must
know what they are doing. It involves the greatest amount of risk, but in
turn can be the most satisfying portion of the entire experience.
Shot of the frame from the northwest. Historically the barn would have been
positioned here not only to provide a windbreak for the house, but also to
take advantage of the wind in the process of separating grain from chaf.
The frame itself is something beautiful to behold. On one level it is a
group of timbers fashioned together in a purely utilitarian way to provide
the framework for a floor, sheathing and a roof. But these elements have a
harmony that transcends mere practicality. The skill, strength and stamina
necessary to assemble these elements into a workable form seem interwoven
into the joinery, the sight lines and the image.
Some of the joinery detail.
It would be wonderful to just let it stand in the sun so that people could
stop by and admire the craftsmanship that results from a few simple tools, a
good eye, and hard work. We have taken our photos and recorded our images for
the VCR, but the direct experience of watching these gifts from the forest
come together in an ensemble of primitive but self-assured conviction is an
experience that has few equals.
Once the frame is covered, light cannot penetrate the corners, the marks of
the broad ax seem less pronounced and the aura of the frame is muted.
Although these monarchs of the forest that once reached for the sky have met
a premature demise, they now provide shelter and usefulness for the human
mechanics that carried them from the woods and gave them a new identity.
Although the fauna that will soon inhabit the rooms, cavities and recesses
are of domesticated breeding and design, there is no stopping the wild
creatures that will soon nest in the foundation stone, spin webs in the
dusty slants of sunlight and take up residence in rafter pockets.
It is this brief period when the frame stands naked in the sun's radiance
that nature, toil, craftsmanship, artistry, poetry and physics all seem
joined into a unifying whole. It is the best time to understand how these
timbers have cheated the forces that sought to return them to the forest
floor and with human vigilance they now have an extended life span, a brief
immortality. And regardless of the calculations, the measurements and the
finite delineation of joinery and line, there is still this realm of the
mysterious. The human endeavor that has brought these elements together with
a harmony and intuition that cannot be completely explained or understood,
is a tradition that should not be broken.
The Society produced a video of the 1999 Barn Raising during the
June 12-13, 1999 Spring Festival at the Bement-Billings Farmstead in Newark
Valley, New York. During these two days the frame of an English threshing
barn built in the period of 1825 to 1830 was brought back to life. See
this and other videos on the Video Tapes page.
Anyone interested in more information regarding the project should e-mail Ed Nizalowski at
EDNIZ@prodigy.net or call (607)
642-8075.
For online resources for barn restoration and related information, visit our
Historians & History Resources
section.